Dismantle and Removal of Asbestos Sheets at Petrobel Fields, South of Sinai (Second and Final Stage).

  1. Date of Signing Contract: October 2009.
  2. Contract role: Main Contractor.
  3. Contract Duration: 18 Months.
  4. Date of Completion: March 2011 extended to the end of 2012.
  5. Value of the total contract at completion: Approx. 0.4 million L.E.
  6. Name of Employer: Petrobel Company.
  • Untitled-1